Flatiron Construction officials say the bridge could be complete in as early as 10 days and that workers are putting the final touches on the new bridge.
If the bridge is completed by Sept. 16, it would be more than 100 days ahead of schedule. The contractors could earn a bonus of up to $27 million if the bridge opens by September 15.
Just because the bridge is finished, Minnesota Department of Transportation officials caution that it doesn’t mean the bridge will open right away.
Officials said they should know the status of the bridge by early next week.